Thank you for visiting the blog. It is dedicated to the 2025 storm restoration project. Please refer to the map for reference as to when your area of the community will be worked on. Please visit the blog periodically for project information, answers to frequently asked questions, and project status updates. We appreciate your patience during the project. 

 

Project links “Click to view”

RCA- Shingle Replacement Notice

landmark-series-brochure-00-00-133-NA-EN-2302-nc-v2

 

 

On-site Project Manager Henry Hernandez

Cell: 612-638-8700

 

 

Shingle color selected by the Board

“CertainTeed Landmark”

Weathered Wood

 

Equipment to be used during the project

 

All dates and proposed plans are “Weather Permitting” and subject to change with little notice

 

On Monday, May 19th, the community-wide restoration project is scheduled to begin. This project is expected to take approximately 50 working days (10 weeks) to complete all of the work.

If you have a satellite dish on the roof that is no longer in service. Please email [email protected]  with your address, and we will remove and dispose of the dish properly. If your dish is still active, it will be disconnected to replace the roof. You will lose service until the roof work is complete and the dish is realigned. 

The work will consist of a full roof replacement with exhaust vent rework as well as gutter and downspout replacement. Unfortunately, with all construction projects, there will be an impact on your daily routine, and your patience and cooperation will be needed. Project notices are posted in the blog, emailed out, and posted on garage doors as a final reminder before work starts on your building. Please read the notice for what to expect and what is requested from you to ensure the work is completed promptly and so you are properly prepared. Henry Hernandez is your dedicated project manager. He will be on-site every day to oversee the work and address residents’ concerns. He can be reached at 612-638-8700.

The work will start on the 10 quad-home buildings on Quebec Ave and continue around the perimeter of the community. As soon as these buildings are completed, 8 buildings in the middle of the community will be worked on. All buildings have been assigned a number on the project progression map. The crew will start on building 1 and work numerically through the community per the map.

Once the roof work is completed, the gutter crew will be on-site to replace the gutters. They are scheduled to begin on Monday, June 2nd. They will also work numerically through the community, following the path of the roofing crew.

Building 1 (14633, 14637, 14641, and 14645 Quebec Ave) will be the first building to be worked on. The crew will be on-site Monday, May 19th, with work starting at 7:00 AM.

In advance of work starting, a storage container, equipment, on-site restrooms, and materials will be delivered and staged around the community. The main staging area to start will be near 7544 Parkridge Pl and will take up the guest parking spots near the building and green space. 

Please contact 612-254-7373 or Email [email protected] with any questions or concerns.