Primrose At Bailey’s Arbor 2019 Asphalt shingle project

 

 

Thank you for visiting the blog. It is dedicated to the 2019 asphalt shingle project. The above 11 homes are scheduled for roof replacement. Please visit the blog periodically for answers to frequently asked question and project status updates. We appreciate your patience during the project. 

On-site project manager Brian Maas can be reached directly at 612-990-3087

 

Please contact 612-254-7373 or Email Info@Atlasmn.com With any questions or concerns. 

 

Project links

BPR- Roofing proposal (click link to view)

 

Atlas roofing project (What to expect) (click link to view) 

 

Job completed!

All building permits have been signed off on and all 4-star extended warranties have been registered. 

Thank you for choosing Atlas to complete your exterior renovation. Please contact us for any future exterior restoration projects. Thank you! 

 

Tuesday 5/14/2019 With perfect weather to start the week, we should have everything wrapped up tomorrow. We started working on three homes at a time to make up for the lost rain day. The completed homes look great!

 

Friday 5/10/2019 The homes started and roof loaded yesterday will be completed today. By the end of the day today, there will be a total of 6 homes completed to this point. On Monday, May 5th we will begin working on 3826, 3824, and 3816 Lilac Court as we will attempt to get back on schedule. Have a great fishing opener and Mothers day weekend!

 

Thursday 5/9/2019 After a very rainy Wednesday, we are going to get back to work. Our plan for today is to begin working on 10767 Oak Grove Blvd. as well as 3830 Lilac Ct. & 3890 Lilac Ln. If the crews are unable to complete the homes they will be finished up tomorrow. 

 

Wednesday 5/8/2019 No work was completed due to the rain. 

May 7th thru May 13th forecast

 

Monday 5/7/2019 The crews began work as planned yesterday and were almost able to get both homes done in a day. They will finish up10547 Hawthorn Court. & 10814 Hawthorn Trail. today and begin working on 10791 Oak Grove Blvd. Materials will be roof loaded on 10767 Oak Grove Blvd but no work will take place with rain in the forecast for Wednesday and Thursday. 

 

Weather permitting, we are scheduled to begin working on the first two home on Monday, May 6th, 2019. Our goal is to complete two homes per working day until all 11 homes are completed.

 

The address completion order is a follows: 

 

Day 1: 10547 Hawthorn Court. & 10814 Hawthorn Trail. 

Day 2: 10791 Oak Grove Blvd & 10767 Oak Grove Blvd.

Day 3: 3890 Lilac Lane & 3830 Lilac Court. 

Day 4: 3824 Lilac Court & 3826 Lilac Court. 

Day 5: 3812 Lilac Court & 3816 Lilac Court.

Day 6: 3810 Lilac Court. 

 

Project staging area located on the side street near 3890 Lilac Lane. 

The material trailer and on-site sanitation will be here for the duration of the project. 

 

Please contact 612-254-7373 or Email Info@Atlasmn.com With any questions or concerns.